May Pen To Williamsfield Leg Of Highway 2000 Is 64 Per Cent Complete
over 3 years in Mckoys News
Work on Phase 1C of Highway 2000, which is being executed under the Southern Coastal Highway Improvement Project (SCHIP) from May Pen to Williamsfield, is 64 per cent complete. Managing Director of the National Road Operating and Constructing Company (NROCC), Stephen Edwards, told JIS News that elements of the project are at various stages of development. These include earthworks – approximately 87 per cent, bridge construction – approximately 86.25 per cent, box and pipe culvert construction – approximately 85 percent, jersey barrier construction – approximately 27 per cent, and asphalt paving – approximately 19 per cent completed. Mr. Edwards pointed…