Demolition delayed at 2 Ferry Dock Hill

over 5 years in theobserver

The demolition of 2 Ferry Dock Hill is taking longer than expected. While in part due to COVID-19, the primary contractor for the project didn’t follow through, an update from City of Sarnia solicitor Sutheat Tim explained. Se7en Hills Inc. won the demolition contract for $168,500 in January, but “did not mobilize the required resources […]